Thursday, 31 October 2013
First concrete went in today
As the weather seems to be helping the work, we had the first layer of concrete put today for the foundations...
Wednesday, 30 October 2013
More foundations photos
Here are some photos of the initial work in the foundations on the east side of the plot. We can already see some of the structure that will take the first layer of concrete tomorrow.
Early work for the fundations
We are now at full speed to start with the foundation, let's hope no more heavy rain!!
Sunset is just lovely....
Sunset is just lovely....
Tuesday, 29 October 2013
Saturday, 26 October 2013
Weekend update
Due to the middle of the week rain and landslide, a pump to remove the water has been working since Saturday. The landslide also implicates more work to correct the already established walls. Only hope is that it doesn't rain that much in the coming weeks...
In the last 2 photos it's quite noticeable that impact of the rain on the actual road in from of the house, again demonstrating how poor the soil is there...
In the last 2 photos it's quite noticeable that impact of the rain on the actual road in from of the house, again demonstrating how poor the soil is there...
Friday, 25 October 2013
2 days of rain - more delays!
Due to the rain there was a landslide that (on top of all the water that is there) will make us lose more time. Thanks S. Pedro!!